Spring 2022 Preliminary Road Work Schedule- Updated 5/12/2022
We know that nobody loves road work, but we want to improve our infrastructure, so it must be done! Below is a preliminary schedule for road work that will take place from approximately May 16 thru June 9th. Please keep in mind that this schedule is subject to change, and we will provide updates via Facebook and the City’s website as they are available. City engineers will also be hanging door tags in affected neighborhoods 24 hours before work begins.
May 16-17
Tie in on Lagoon St. & Start laying pipe on 400 E.
May 18-19
Lay pipe on 100 S.
May 23-24
Lay pipe on 200 E.
May 25-26 & 30
Lay pipe on 100 W.
May 31- June 2
Lay pipe on 100 N.
June 6-9
Finish any piping, test and chlorinate lines
*This is a preliminary schedule and is subject to change as the project proceeds. City engineers will be placing door hangers in affected neighborhoods 24 hours prior to work beginning in that area. Progress updates will be posted on the City's Facebook/Website as they are available.