Construction Updates

Posted on: April 18, 2023

[ARCHIVED] State Street Reconstruction Project

An infographic displaying estimated road reconstruction schedule

State Street Reconstruction Project 2023 Information

April 19-27 Start:
Irrigation Line Installation, Install Water Services, Block Retaining Wall Installation

May 2-12 Start:
Install Air Release Station,  Relocate Fire Hydrants, Shoulder Reconstruction & Widening, UTCB Roadway, Demo./ Install Concrete Sidewalk.

May 15-30 Start:
Install Concrete Curb and Gutter, Concrete Prep Sidewalk Driveway, Demo/ Install Concrete Driveway

June 2-20 Start
Pedestrian Ramp Installation, Patch Paving, Roadway Widening  Paving, Chip Seal Application,  Fence Relocation & Installation, Relocate Cluster Mailbox, Sign Installation

June 20-29 Start:
Relocate Valve Boxes & Manhole, Reconstruct Manhole & Boxes, Pavement Marking (1st application), Sod Installation

August 9 Start:
Pavement Marking (2nd application)

Please visit the Public Works page  for available project updates. 