State Street Reconstruction Project 2023 Information
April 19-27 Start:
Irrigation Line Installation, Install Water Services, Block Retaining Wall Installation
May 2-12 Start:
Install Air Release Station, Relocate Fire Hydrants, Shoulder Reconstruction & Widening, UTCB Roadway, Demo./ Install Concrete Sidewalk.
May 15-30 Start:
Install Concrete Curb and Gutter, Concrete Prep Sidewalk Driveway, Demo/ Install Concrete Driveway
June 2-20 Start
Pedestrian Ramp Installation, Patch Paving, Roadway Widening Paving, Chip Seal Application, Fence Relocation & Installation, Relocate Cluster Mailbox, Sign Installation
June 20-29 Start:
Relocate Valve Boxes & Manhole, Reconstruct Manhole & Boxes, Pavement Marking (1st application), Sod Installation
August 9 Start:
Pavement Marking (2nd application)
Please visit the Public Works page for available project updates.