Construction Updates

Posted on: April 18, 2023

[ARCHIVED] State Street Reconstruction Project

An infographic displaying estimated road reconstruction schedule

State Street Reconstruction Project 2023 Information

 BELOW IS AN APROXIMATE TIMELINE OF START DATES FOR THE RECONSTRUCION PROJECT TAKING PLACE ON STATE STREET BETWEEN 800 AND 300 SOUTH

April 19-27 Start:
Irrigation Line Installation, Install Water Services, Block Retaining Wall Installation

May 2-12 Start:
Install Air Release Station,  Relocate Fire Hydrants, Shoulder Reconstruction & Widening, UTCB Roadway, Demo./ Install Concrete Sidewalk.

May 15-30 Start:
Install Concrete Curb and Gutter, Concrete Prep Sidewalk Driveway, Demo/ Install Concrete Driveway

June 2-20 Start
Pedestrian Ramp Installation, Patch Paving, Roadway Widening  Paving, Chip Seal Application,  Fence Relocation & Installation, Relocate Cluster Mailbox, Sign Installation

June 20-29 Start:
Relocate Valve Boxes & Manhole, Reconstruct Manhole & Boxes, Pavement Marking (1st application), Sod Installation

August 9 Start:
Pavement Marking (2nd application)

Please visit the Public Works page  for available project updates. 